HomeMy WebLinkAboutCouncil Resolution 545RESOLUTION NO. 545
A RESOLUTION GRANTING PRELIMINARY PLAT APPROVAL
FOR JACKSON CREEK ESTATES SUBDIVISION
UNIT NO. 3
WHEREAS, Tom Malot, hereinafter referred to as Subdivider,
has submitted a preliminary plat for Jackson Creek Estates Unit
No. 3, a subdivision located in the southwest quadrant of the
City at the proposed location of the extensions of Vincent. Avenue
and Brandon Streets, more particularly described in the Jackson
County Tax Assessor's records as 37 2W 10 TL 3100, and
WHEREAS, the Planning Commission of the City on May 1, 1990
reviewed said application and by Planning Commission Resolution
No. 191 recommended approval of said preliminary plat, subject to
the conditions set forth in the staff report, which conditions
are attached hereto, marked Exhibit A, and which are by this
reference incorporated into the within resolution, and
WHEREAS, the City Council of the City of Central Point held
a public hearing upon said application for approval of
preliminary plat on May 17, 1990, pursuant to Central Point
Municipal Code Section 1.24.020D, and having at said public
hearing received and reviewed the City staff report, the Planning
Commission report and resolution, and public hearing evidence,
and being fully advised, now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF CENTRAL
POINT, OREGON, AS FOLLOWS:
Section 1. Based upon the staff report, Planning Commission
report and resolution, and evidence relating to said application,
RESOLUTION NO. 545 - 1
(JACKSCRK.REV - 051490)
the City Council hereby finds that said application meets the
requirements for preliminary plat applications, that said
preliminary plat as proposed is in compliance with the City's
Comprehensive Plan and Zoning Code, and if the conditions set
forth hereinafter are met, said. application meets the City's
requirements for subdivision layout, park. dedication, street
standards, water system standards, sanitary sewer standards and
storm drainage standards.
Section 2. The City Council hereby grants approval to the
preliminary plat submitted by Subdivider for Jackson Creek
Estates Unit No. 3, subject to the conditions set forth in
Exhibit A, attached hereto, and subject to execution of a
subdivision agreement by Subdivider agreeing to completion of
said conditions.
Section 3. The Mayor is hereby authorized and directed to
execute said subdivision agreement and all other documents on
behalf of the City in connection with the within preliminary plat
approval.
Section 4. This action of the Council shall be noted on two
copies of the preliminary plat, including reference to the
conditions set forth in Exhibit A, with one copy to be returned
to Subdivider and one copy to be retained in the City planning
files with a memorandum setting forth the action of the Council,
as required by Central Point Municipal Code Section 16.24.080..
Passed by the Council and signed by me in authentication of
its passage this ~~ day of
ATTEST:
City Repr enta~ive
APPROVED by me this
RESOLUTION NO. 545 - 2
(JACKSCRK.REV - 051490}
EXHIBIT_.A
Page 1 of 3
CONDITIONS
JACKSON CREEK ESTATES UNIT NO, 3
1. Street name signs including posts, labor and equipment for installation
of street signs shall be paid for by the developer of this subdivision,
and the installation shall be completed. by the City.
2. A traffic control signing plan shall be included as part of the final
construction plans, and will. be installed by the City and all costs
associated with traffic control sign installation shall be paid for by
the Developer.
3. A soils engineer must evaluate the strength of the soil (R-value) to
determine the street section design. The City's engineer shall be used,
and the developer shall pay for the costs of these services. A design
life for Vincent Street in the subdivision with a minimum 20 year life,
given a daily traffic volume not to exceed 1000 vehicle trips per day
and 2% truck traffic shall be used. A design life for Brandon Street
shall be a minimum 20 year life given a daily traffic volume of 2500
vehicle trips per day and 2% truck traffic.. All other streets shall be
designed for a 20 year life, a daily traffic volume of 1000 vehicle
trips per day and 2% truck traffic,
4. A street lighting plan shall be included in the construction documents
according to the requirements of PP&L. All intersections shall be
illuminated. Street light shall be located no greater than every 300 ft.
Developer to install. all pads and conduits for street lights as a part
of the construction of the subdivision. The developer shall also pay
for street lights and for the installation of all street lights in this
subdivision.
5. The developer shall construct a valve at the end of the street in this
phase for the future connection of the next phase of this development.
6. Ladder rungs shall be installed in each sanitary sewer manhole of a
depth greater than 3.0 feet to the flow line of the manhole. Developer
shall use ladder rungs approved by the Central Point Public Works
Department.
7. There is a small seasonal stream which flows through this property at
its northern property line. Developer shall construct a storm drainage
system which collects the flow from this subdivision and carries through
this subdivision in such a manner as to not cause flooding of any lot
in a drainage area of this seasonal stream.
8. According to the Master Plan for Jackson Creek Estates, a 15" storm pipe
would cross between Lot 69 and 70. The storm sewer will cross lot 70
and 71 and discharge directly to Griffin Creek. Also a 24" storm pipe
would cross the park property between Lot 80 and 123. This storm pipe
shall be located 10' north of the north property line of lot 123.
EXHI6IT A
Page 2 of 3
9. Catchbasins must be located. no greater than 350 feet for any section of
curb and gutter.
10. Developer shall design the storm drainage system to provide for
discharge of properties in future phases or within the drainage service
area of this subdivision's storm drainage system. The developer shall
follow the storm drainage plan done as a part of the Stonecreek
Subdivision No. I Master Plan, a copy of which may be obtained at Public
Works Department in Central Point City Hall..
11. As originally approved. in Jackson Creek Estates Unit #1, the developer
shall provide park land in lieu of paying a $200.00 per lot development
fee for property located along Griffin Creek as a part of the Park
Master Plan. This property is to be dedicated as the requirements set
forth in Title 16.20. Based on Title 16.20, 700 square feet per lot or
a total of 45,500 square feet (65x700 = 45,500 square feet) shall be
dedicated.
12. The developer shall install or cause to install conduits for utilities
at intersections or 1'ocations determined by utility companies and
utility companies who will not install their services until after the
subdivision is constructed. The developer shall be responsible for all
costs associated with the installation of these conduit crossings.
13. A Subdivision Agreement shall be approved by the City Council prior to
issuing a permit for construction of this subdivision.
14. All construction for utilities, streets and other structures discussed
herein within rights of ways owned or to be owned by the City of Central
Point, shall be done according to all rules, regulations, ordinances,
resolutions, and other applicable requirements of the City of Central
Point for construction of this Subdivision.
15. The final plat for this Subdivision shall not be approved by the City
Council until all conditions as herein stipulated and as approved for
this Subdivision have been met.
16. The preliminary plat review for the preliminary plat submitted herein
by Tom Malot Construction was done in accordance with the rules,
regulations and ordinances in effect as of the date of this review. Any
modifications by the developer which would allow this Subdivision not
to meet standards set forth in the Central Point Municipal Code or would
require staff to complete a new preliminary plat review, shall require
a new submittal of preliminary plat for City approval.
17. If it is determined that 1000 gpm is not attainable for fire flow in
this subdivision, the developer shall make the necessary corrections to
the existing water system within this subdivision to obtain the required
fire flow. The correction(s) shall be completed as a part of the
construction of this subdivision.
EXHIBIT A
Page 3 of 3
18. The developer shall indicate direction of Griffin Creek flow.
19. The developer shall. propose the name for the new streets in the
Subdivision for City of Central Point approval.
20. The developer must remove the 1 ft, reserve strip from Unit No. 2.
21. A 25 ft. clear vision area at all intersections shall be noted on the
preliminary plat and provided as apart of the subdivision construction
plans.