HomeMy WebLinkAboutVilas Reservoir Irrigation Relocation Visar ConstructionCONTRACT FOR CONSTRUCTION
This contract, made and entered into this 1st day of July 2011, by and between the CITY OF
CENTRAL POINT, OREGON, hereinafter called the "OWNER", and Stan Sesar of Visar
Construction ,hereinafter called the "CONTRACTOR".
WITNESSETIi;
Said Contractor, in consideration of the sum. and/or unit prices to be paid to himlher by the
Owner, and of the covenants and agreements herein contained, hereby agrees, at his own proper
cost and expense, to do all work and furnish all materials, supplies, supervision, labor, tools,
equipment, transportation and incidentals, and shall pay all applicable taxes and fees necessary
for the completion of the construction of the Vilas Reservoir Irrigation Relocation, in the City of
Central Point, Oregon, for said Owner, to the extent of the Proposal, with unit prices filled in
made and submitted by the Contractor on the 1st day of J~ 2011, all in full compliance with
CONTRACT DOCUMENTS, which includes: The Advertisement for Bids, the Information and
Instructions for Bidders, the Bidders Proposal and the Bid Bond, the Performance and Payment
Bond, the General Conditions, the Special Provisions, Special Specifications and the applicable
portions of the City's Public Works Standard Specifications and Details, included herewith, and
in accordance with the Plans prepared by Public Works Management for the City of Central
Point, Public Works Department, dated May 11,2011, entitled: Vilas Reservoir Irri ag tion
Relocation which Plans and aforementioned Contract Documents are hereby referred to, and by
reference made a part of this CONTRACT FOR CONSTRUCTION as fully and completely as if
the same were fully set forth herein, and axe mutually cooperative herewith. In consideration of
the faithful performance of the work herein set forth, and in accordance with the directions of the
Engineer, and to his satisfaction as provided herein, the Owner agrees to pay to the Contractor
the amounts bid in the Proposal, adjusted in accordance with the General Conditions, and to
make such payments in the manner and at the times provided for in the General Conditions.
Before starting work, the Contractor and subcontractors shall each file with the Construction
Contractors Board, and maintain in full force and effect, a separate public works bond, in the
amount of $72,791.50 unless otherwise exempt, as required by ORS 279C.836 and
OAR 839-025-0015. The Contractor shall verify subcontractors have filed a Public Works Bond
before the subcontractor begins work.
The Contractor agrees to complete the work within the time limits as specified herein and to
accept as full payment the amounts set forth in the Proposal and computed in accordance with
the Contract Documents.
It is agreed that the Contractor shall complete the work in all respects by the following schedule:
Complete all work by October 31, 2011.
In the event the Contractor shall fail to complete the work within the time limits or the extended
time limits agreed upon, liquidated damages shall be paid to the Owner in the amount of $400.00
~~
;.:per day until the work is completed as set forth in the Contract Documents and to the satisfaction
of the Engineer. Sundays and legal holidays will be excluded when determining days in default.
The Contractor agrees to hold harmless the City from, and to repair and replace (as directed by
the City's Public Works Director) any and all defects and deficiencies which develop in
workmanship and/or materials for a period of two (2) years or as stated in the special
specifications after the date of the written notice from the Engineer of the final acceptance of the
project by the City.
IN WITNESS THEREOF, we, the parties hereto, each subscribes the same this
~, ~~-,_ day of ~ ~ ~'~' 2011.
CITY OF:.CENTRAL POINT:
B
(City Administrator)
~ ~ ~/
CONTRACTOR:
~~
(Co pany Name)
4 ~ ~ ~...
Title: ~~ ~~~.C ,~.;..: