HomeMy WebLinkAboutOct 10 2017 CAC PacketCITIZENS ADVISORY COMMITTEE
Tuesday, October 10, 2017 - 6:00 p.m.
Council Chambers @ Central Point City Hall
I. MEETING CALLED TO ORDER
H. ROLL CALLIINTRODUCTIONS
David Painter (Chair), Sam Inkley, Jr., Larry Martin, Cameron Noble, Cindy Hermes,
Patrick Smith and Caitlin Finley
M. MINUTES
Review and approval of August 15, 2017 minutes
IV. PUBLIC APPEARANCES
V. BUSINESS
VI. DISCUSSION
A. Open discussion about a Conceptual Land Use and Transportation Plan for
Urban Reserve Areas CP -5 and CP -6; Applicant City of Central Point
VII. MISCELLANEOUS
A. Central Point Development Update
VIII. ADJOURNMENT
City of Central Point
Citizens Advisory Committee
August 15, 2017
1. MEETING CALLED TO ORDER AT 6:10 P.M.
11. ROLL CALL
Present were: David Painter, Larry Martin, Cameron Noble, Cinda
Harmes, Pat Smith, Sam Inkley and Caitlyn Finley
Also in attendance were: Tom Humphrey, Community Development
Director, Don Burt, Planning Manager, Molly Bradley, Community Planner and
Karin Skelton, Planning Secretary
III. MINUTES
Pat Smith made a motion to approve the minutes of July 11, 2017.
Cameron Noble seconded. All members said "aye". Motion approved.
W. PUBLIC APPEARANCES - NONE
V. BUSINESS
A. Consideration of Land Use Element, City of Central Point
comprehensive Plan. Applicant: City of Central Point; File No.: CPA -17003
Planning Manager Don Burt said that at the previous Citizen's Advisory
Meeting a working draft of the Land Use was presented and discussed. The
discussion focused on changes needed to reflect prior land use actions that
affected land use goals and policies that are not consistent with the current
Land Use Element. Also discussed were changes necessitated by recent
policy, which are primarily related to residential land uses and the need to
adjust the minimum density requirements of the Regional Plan Element.
Additionally he said there are changes that are recommended to provide
more flexibility in the land use process which are related primarily to the
commercial lands and are intended to provide a broader purpose base
allowing for more flexibility in responding to structural changes in the
commercial sector of the economy.
He explained the Land Use Element was intended to track land use activity and
he identified the Land Use Element Goals.
CAC Minutes
August 15, 2017
Page 2
Mr. Burt gave an overview of the Regional Plan Element and how each of the
Urban Reserve Areas was required to have a Lanz! Use and Transportation
Concept Plan prior to being brought into the City. He explained the relationship
between the Regional Plan and the other elements.
Community Development Director Tom Humphrey stated that the Citizen's
Advisory Committee would be reviewing the Concept Plans for some of the
Urban Reserve Areas in October.
Mr. Burt reviewed the Land use classifications:
Residential, which includes very low density, low density, medium density and
high density zoning.
Commercial, which includes Neighborhood Commercial, Employment
Commercial. He said that the current land use titles for the Tourist &
Professional Office and Thoroughfare Commercial are outdated, and should be
replaced with Employment Commercial and General Commercial. The purpose
of the Central Business District overlay is to emphasize the downtown as a
unique place in the City.
Industrial, which includes Light Industrial and General Industrial zoning.
Civic, which includes public facilities such as schools, city hall, community
centers, etc. He said currently Civic zoning includes churches, and similar uses
which are not public. Consideration is being given to eliminating all but public
facilities from this classification. Typically churches are allowed in other districts
as a conditional use, and will be allowed to continue as such.
The Committee asked where churches would be allocated and Mr. Burt replied in
residential zones.
Mr. Burt said the C-4, Tourist & Office -Professional Commercial district is
intended to provide for the development of concentrated tourist commercial and
entertainment facilities and also for the development of compatible professional
office facilities.
He stated that the Parks & Recreation/Open Space includes public parks, open
space and environmental lands such as flood plains, steep hillsides, etc.
Currently this classification includes only public parks and open space, but there
are incidences where lands are committed to open space for flood plain or other
environmental reasons. It is proposed that these lands, when identified be
included in the parks and recreation/open space classification.
3
CAC Minutes
August 15, 2017
Page 3
Right of Way includes public streets and private streets.
Mr. Burt said that the Land Use Element would cover the years 2017 to 2037. It
would be based on a current population of 17,585 with a target population of
23,085. This would be a population increase of 5,500. He said that Portland
State University updated the population estimates every four years and that
number determined how much additional land would be needed.
He reviewed the mapping changes with regard to the Comprehensive Plan and
the goals and policies for each land use classification.
Cinda Harmes made a motion to favorably recommend the working draft of the
Land Use Element to the Planning Commission and the City Council. Caitlin
Finley seconded the motion. All members said "aye". Motion passed.
Mr. Burt said that in the future the Committee would be hearing about the
Urbanization Element which concerned planning the growth of community. He
said that the Urbanization Element would need to be done at the same time as
the Public Facilities Element.
Tom Humphrey explained that in October the CAC would be seeing draft concept
plans for CP -5 & CP -6 which were located west of Grant Road.
Additionally, he explained the role of the CAC for the benefit of the new
members.
VI. DISCUSSION
A. Current Development Update
Mr. Humphrey updated the committee on the progress of the Costco building,
and the veterinary hospital. He said that Microdevices would be relocating to
Central Point from Medford and that the Rogue Federal Credit Union was
nearing completion. He added that there was an elder care and memory facility
in Twin Creeks that was in the process of obtaining building permits. He stated
that the apartments in Twin Creeks had been approved and would be going
forward. He said there had been quite a bit of concern in the neighborhood
regarding the noticing of the project so there would be some changes to the
noticing requirements
CAC Minutes
August 15, 2017
Page 4
VII. MISCELLANEOUS
VIII. ADJOURNMENT
Cameron Noble made a motion to adjourn. Pat Smith seconded the motion. All
parties said "aye". Meeting adjourned at 7:12 p.m.
The foregoing minutes of the August, 2017 Citizens Advisory Committee were
approved by the Citizens Advisory Committee at its meeting of October 10,
2017.
Chairman
STAFF REPORT
AGENDA ITEM: File No. CP -17001
Ap
CENTRAL
POINT
STAFF REPORT
October 10, 2017
Planning Department
Tom Humphrey,AICP,
Community Development Director
Open discussion about a Conceptual Land Use and Transportation Plan for Urban Reserve Areas CP -5 and CP -6;
Applicant: City of Central Point.
STAFF SOURCE:
Tom Humphrey AICP, Community Development Director
BACKGROUND:
The City's Regional Plan Element includes a provision that prior to expansion of the urban growth boundary into an urban
reserve area it is necessary to adopt conceptual land use and transportation plans for the affected urban reserve. The City
received a request to add Urban Reserve Area CP -6 to the City's UGB for additional housing creation. The City Council
responded to this request by passing a Resolution of Intent to initiate a UGB Amendment_
City staff is initiating this preliminary discussion with the Citizen's Advisory Committee in order to create a concept plan
that reflects local land use expectations and remedies for traffic congestion the land uses may generate. The City agreed to
a residentiallemploymentlopen space split in the Regional Plan (76°Io, 4% and 18% respectively). That means there about
337 acres that can be designated for residential uses and about 18 acres designated for employment. The Corrunittee will
be asked for their opinions about the uses they would like to see given the constraints that exist in this area. Existing city
land uses and environmental constraints are reflected in the draft Conceptual Plan and maps.
ISSUES:
Public Comment on the CP -516 Conceptual Plan will be received at the Citizen Advisory Committee [CAC} if citizens
choose to attend and then again at the Planning Commission meeting when a draft is complete. Based on land owner and
CAC input, the Planning Commission will make a recommendation to the City Council,
EXHIBPTSIATTACHMENTS :
Attachment "A — Excepts from City of Central Point Regional Plan Element"
Attachment "B — CP -516 Draft Concept Plan„
ACTION:
Discuss localized constraints, land use expectations and transportation options for the CP -5/6 Concept Plan.
RECOMMENDATION:
Direct staff to refine a draft conceptual plan based upon public input received at the CAC meeting.
Page 1 of 1
ATTACHMENT "-A..._"
At the northeast corner of CP -41) there is a one -acre parcel of exception land zoned Ur-
ban Residential (UR -1). This property has an existing residence and abuts the City limits
and residentially zoned lands to the
east. The property also abuts agri- k'.
Bear Creek (CP -4D)
cultural lands to the north. As an ex-
ception area, it was deemed appro- •
priate to include the property with- - -t V
in this Urban Reserve as first priori-
ty land. However, it is recognized
! 1 -
that the property abuts agricultural
_
land and as such, future develop-
ment of the property will be subject
to compliance with the agricultural r - J
buffering standards to be imple-
mented as part of this Plan. Because
r�
of the existing residential character
of the property; and its proximity to h t
other developed residential lands, it
was deemed appropriate to include
this parcel in CP -41).
Reasonably Residential Aggregate Resource Open
Developable Space/Parr
Acres: 52
I Proposed Uses 1% 0% 0% 99°x6 0% 1
AREA CP -5 (GRANT ROAD AREA)
Area CP -5 has approximately 31 acres lo-
cated immediately west of city limits, east
of Grant Road, and south of Scenic Avenue.
Most parcels within the area are designat-
ed as Rural Residential exception land. A
10 -acre parcel is designated as Agricultur-
al land at the area's southern end. The
parcel contains a walnut grove, Christmas
trees, and a dwelling with accessory uses
located southwest of the creek. A small
pasture and two barns are on the creek's
opposite side. Because the creek runs
through the property and portions are in
residential use, the property's effective
farmabie portion is significantly less than
ten acres; no adjacent parcels are available
for farm use in conjunction with this prop -
Grant Road Area (CP -5A)
Gross Acros:31 Reasonably Residential Aggregate Resource open employment
Developable Space/Parks
Acres: 19
Proposed Uses 91% 0% 0% 9% 0%
City of Central Point
Regional Plan Element Page 12 of 26
erty. Jackson Creek and its associated 100 -year floodplain follow Grant Road except
where they cut through the EFU parcel. The riparian areas create a significant physical
barrier from the larger tract of farmland to the west and reduce the need for fencing.
Consequently, the area can and will provide for urban needs in a manner that is compat-
ible with nearby agricultural lands. There are no nearby forest lands or uses.
AREA CP -6A (TAYLOR ROAD AREA)
This area consists of 444 acres. The CP -6A area is adjacent to city limits, and could easily
be served by services from the Twin Creeks TOD or from existing collector roads, such
as Beall Lane, Taylor Road, and Scenic Avenue. The circulation plan for this area is a
natural extension of the Twin Creeks TOD, and of historic east -west roads such as Tay-
lor and Beale.
Public water, sanitary sewer and natural gas maps indi-
cate that this infrastructure can be readily, efficiently,
and economically extended to CP -6A from the east and
the south. Storm drainage can be developed, treated,
and effectively discharged into existing systems. The
Twin Creeks TOD uses passive water treatment. Central
Point intends to require passive water treatment for
new development in this area.
Approximately two-thirds of the land in this urban re-
serve is currently designated for agriculture, and was
recommended by the RLRC as part of the Commercial
Agricultural Base. The remaining one-third consists of
exception lands planned Rural Residential. Soils in this
area are Class 3 with limited amounts of Class 2. Agri-
cultural use has been limited to livestock grazing or has
otherwise remained fallow.
Taylor Road Area (CP -6A)
Gross Acres: Reasonably Residential Aggregate Resource Open Employment
444 Developable Space/Parks
Acres: 386
Proposed Uses 76% 0% 0% 20% 4%
The area is generally free of any severe environmental constraints that occur elsewhere
around the City, and proximity to the downtown core is conducive to urban centric
growth objectives that minimize vehicle trip lengths and durations and the same repre-
sents a positive consequence under all of the ESEE factors. Central Point's experience
with TOD design on the west side of the City has been extremely positive and has fos-
tered positive social relationships in the community. In the balance, it is concluded that
the comparative ESEE consequences for urbanization are positive. In combination with
the other Goal 14 location factors, CP -6A is determined to be suitable and appropriate
as an urban reserve. The City believes that there are more natural linkages from the ar-
eas west of Grant Road to the Downtown core and many other Central Point neighbor-
hoods.
City of Central Point
Regional Plan Element Page 13 of 26
ATTACHMENT u -IL"
Wednesday October 4, 2017 Draft
GRANT ROAD AREA
CONCEPT PLAN
A CONCEPTUAL LAND USE AND
TRANSPORTATION PLAN FOR
CP -S/6
AN URBAN RESERVE AREA OF THE CITY OF
CENTRAL POINT
City of Central Point
Adopted by City Council Resolution No.___, December, 2017
Page 1 of 20
PART 1. INTRODUCTION
As part of the Regional Plan Element' it is required that the City prepare and adopt for each
of its eight (8) Urban Reserve Areas (URAs) a Conceptual Land Use Plane and a Conceptual
Transportation Plan 3prior to or in conjunction with an Urban Growth Boundary (UGB)
amendment within a given URA. This document addresses both conceptual plans, which are
collectively referred to as the CP -5/6 Concept Plan (Concept Pion'], Figure 1 illustrates CP -
5/6's relationship to the City and the other URAs.
ceNrwu
POINT
Y rw � • ��L
FWwft I. CenAMI Fant
Legend vdmxNrm. Am
I
As used in this report the
term 'concept plan' refers
to a document setting
forth a written and
illustrated set of general
actions designed to
achieve a desired goal that
will be further refined over
time as the planning
process moves from the
general (concept plan) to
the specific (site
development) . In the case
of CP -5/6 the goal to be
achieved is a first
generation refinement of
how the land use
distributions and
applicable performance
indicators of the Greater
Bear Creek Valley Regional
Plan (GBCVRP) will be
applied to CP -5/6. The
areas of CP -5 and CP -6 are combined in this document given their proximity to one another
and because of CP -5's small size.
The concept plan is a general land use guide prepared in accordance with, and intended to
facilitate implementation of the Regional Plan Element. It does not address compliance with
' City of Central Point Ordinance 1964
2 City of Central Point Comprehensive Plan, Regional Plan Element, Section 4.1 Performance Indicators,
subsection 4.1.7
3 City of Central Point Comprehensive Plan, Regional Plan Element, Section 4.1 Performance Indicators,
subsection 4.1.8
Page 2 of 20
10
the Oregon Statewide Land Use Planning Goals, applicability of land use planning law, or
comprehensive plan compliance. These items will be appropriately addressed at some other
time as the area's planning proceeds through UGB amendment, annexation, zoning, site
plan approval, and ultimately development, with each step being guided by the Concept
Plan.
The Concept Plan illustrates the City's basic development program for CP -5/6; which is
presented in Part 2 of this document. The remainder of the document (Part 3) is dedicated
to providing background information used in preparation of the Concept Plan, including
findings of compliance with the land use distribution and applicable Performance Indicators
in the City's Regional Plan Element.
In summary the Concept Plan has been prepared in accordance with the Regional Plan
Element and Greater Bear Creek Valley Regional Plan including all applicable performance
indicators set forth in these documents. The development concept for CP -5/6 compliments
and supports local and regional objectives relative to land use distribution and needed
transportation corridors identified in the Greater Bear Creek Valley Regional Plan.
PART 2. THE CONCEPT PLAN
The long-term objective for CP -5/6 is that it will develop as another unique residential
neighborhood which creates :a'sense of place` and enhances mixed modes of
transportation. The area is currently occupied by small farms and home sites which are
generally west of the current city limits on Grant Road. The Concept Plan is comprised of
two elements:
a. The Conceptual Land Use Plan ('Land Use Plan')
The primary objective of the Land Use Plan is to refine the land use
categories and spatial distribution of those categories throughout CP -5/6.
This is necessary because the Regional Plan Element only addresses land
use in terms of general land use types, i.e. residential, employment, etc.,
and a percentage distribution of the land use.
The Regional Plan Element distributes land uses within CP -5/6 into three
land use classifications; residential (76%), open space/park (20%) and
employment (4%). Employment land can include two categories in this
case: commercial and civic. The Land Use Plan for CP -5/6 refines these
allocations by aligning them with the appropriate Comprehensive Plan
Land Use and Zoning designations in the City's Comprehensive Plan. Those
designations are illustrated in Figure 2, and tabulated in 1able 1 as follows:
Page 3 of 20
m
i. Residential. The Comprehensive Plan's residential designation is
intended to 'provide an adequate supply of housing to meet the
diverse needs of the City's current and projected households'.
Land Use is broken down into two categories.
• Low density;
• Medium density;
ii. Employment. The Comprehensive Plan's commercial
designation is intended to actively promote a strong, diversified
and sustainable local economy that reinforces Central Point's
`small town feel', family orientation and enhanced quality of
life. Civic uses and convenience centers meet immediate needs
in neighborhoods and reduce out of area vehicle trips.
iii. Parks and Open Space. This Comprehensive Plan designation is
consistent with agricultural buffering in Regional Plan Element
and allows for the continued use and improvement of irrigation
systems and naturai drainage. It also provides opportunities for
passive recreational/open space use.
365.7 06,MRes. R -1141 IA
QVIC
t7.9
roc G0.111. *1
93.6 Park ft NOW SPW
A75.0
b. The Conceptual Transportation Plan ('Transportation
Plan')
The regionally significant transportation documents affecting CP -5/6 are
the Central Point Transportation System Plan (TSP) and the Rogue Valley
Regional Transportation Plan (RTP). The Concept Plan acknowledges these
plans (Figure 2, CP -5/6 Concept Plan) and includes policies that encourage
the thoughtful development of the URA and surrounding properties.
c. Implementation Guidelines
The following guidelines are intended to serve as future action items:
Page 4 of 20
12
f
f
c. Implementation Guidelines
The following guidelines are intended to serve as future action items:
Page 4 of 20
12
Policy CP -5/6.1 Land Use: At time of inclusion in the City's urban growth
boundary (UGB) the property will be shown on the City's General Land
Use Plan Map as illustrated in the CP -5/6 Concept Plan, Figure 2 except
where the concept plan depicts a designation that does not currently
exist in the City's Comprehensive Plan. In such cases, the City may apply
a designation it deems appropriate under its current map designations.
Policy CP -5/6.2 Transportation: At time of inclusion in the City's urban
growth boundary (UGB) the local street network plan, road alignments
and transportation improvements identified in various state and local
plans will be included as illustrated in the CP -5/6 Concept Plan, Figure 2
and where feasible.
Policy CP -5/6.3 Urban Reserve Management Agreement (URMA) and
Urban Growth Boundary Management Agreement (UGBMA): The City
will revisit mutual agreements with Jackson County in order to address
the proliferation of 'marijuana grows' in proximity to urban residential
land uses. The City and County will continue to coordinate land use
activity within planning boundaries.
Policy CP -5/6.4: Committed Residential Density: Upon UGB Expansion
into CP -5/6 and after annexation, the county zoned residential land (e.g.
RR and Uts-l) will become legally non -conforming in 'less dense'
subdivisions. Land use divisions and redevelopment will be encouraged
to support the residential land use densities agreed to in the Regional
Pl*wj, lement. .
Policy CPS/65 Forest%Gibbon Acres Unincorporated Containment
Boundary: The City and Jackson County will have adopted an agreement
(Area of Mutual planning Concern) for the management of
Forest/Gibbon Acres:
Policy CP -5/6.6 Agricultural Mitigation/Buffering: At time of UGB
Expansion into CP -5/6, the City and County will coordinate with RRVID
to identify, evaluate and prepare potential mitigation. The City will
implement agricultural buffers in accordance with adopted ordinances
at the time of annexation.
Page 5 of 20
13
A
CENTRAL
POINT
N
A_ Figure 2. Concept Plan
L.p.na Prop°"r L"d Us* CP -5A and CP -6A
EdWap mW Pt*pddd SRN& meawwnWl Co, Imi
Cs -SA MymNWrl ••••• o,opo.,dcowm, IWFte. Cammrdsl Concept Plan
CP-" = h@w rMW •...• Pmp—d coram (M) WW6rw Rea Cbk
IA�NlLN
Ag euem — Cowam ..... vmp�d Car.,br (ux) ww a« M Paden
dhftks • • • Pmpead MYw AfW M ..... Pmpe d CdAwbr (Mnmre)
UGH
Sft me
Page 6 of 20
14
PART 3. SUPPORT FINDINGS
The findings present in this section provide both background information and address
the Regional Plan Element's Performance Indicators.
a. Current Land Use Characteristics
This section describes the general character of CP -5/6 in its current condition.
Natural Landscape: CP -5/6 is traversed by various creeks and waterways east
and west of grant road which bisects the two URAs. Various ponds and wetlands
have formed along the creeks and some are independent from them.
Topographically, the land in CP -5/6 is flat but gently sloping, to the
north/northeast.
In spite of the numerous creeks, ponds and wetlands present in the URA, there
are relatively few tax lots that are subject to the flood hazards as shown in
Figure 4. The 31 acres that make up CP -5 are most affected by flood hazards
which reduce the total buildable area to roughly 19 acres. Those areas that are
subject to flood zones will be required to perform mitigation.
Cultural Landscape: CP -5/6 is oriented to the west of the current city limits and
the Urban Growth Boundary which is Grant Road. The preponderance of land in
the URAs is Exclusive Farm Use (E FU) and is irrigated by the Rogue River Valley
Irrigation District (RRVID). Active farming is done west of Grant Road consisting
of grazing, truck crops and now cannabis. Other land (approximately 150 acres)
in the URA has been subdivided into rural residential lots (Figure 5) some of
which are served by the Rogue Valley Sewer Service (Figure 6). No city water has
been extended into these URAs.
Page S of 20
M:]
CENTRAL
POINT
FWdvmy
�1 CP -5A
�....�1 CP -6A
AE
Figure 4. Flood Hazard
Urban Reserve Area CP-5A/6A
Concept Plan
Page 9 of 20
17
b. Current Land Use Designations & Zoning
Jackson County zoning acknowledges the unique geographic features of CP -516
by designating land for both agricultural and urban uses, The area's proximity to
The remainder of the land uses in the County's plan are as shown in Figure S.
or
CENTRAL
POINT
L"ad
r
M
I
t
Z"S C RR -10 - UR -1
AN U -W2.5 - U610
AN MW - RR -5 - M30
EFU RC RRM UR4
OR _ 100 M RRS MM
�C Ru Re
a�oa GVRQ
LPN
\1MIW�6 WMnPIAUIIIN64�� u,v PMOKry Yry.KCV� W [vagi RnKPIB C w+v I-��
18
Figure 5. Zoning
Urban Reserve Arm CP-5A16A
Concept Plan
Page 10 of 20
A comparison of the existing and proposed land uses are reflected in Table 2.
Table Z Current ,ind Proposed 7oning
The proposed city zoning will be divided into residential, employment and park
land in keeping with the Regional Plan.
c. Existing Infrastructure
Water
Currently, public water service isnot available to CP -5/6, and will have to be
extended from the Twin Creeks Development, Taylor and Grant Roads.
Sanitary Sewer
CP -5/5 is in the RVSS service area and some sewer lines have been extended
into the Residential areas south of Taylor Road (Figure 6). More lines will have
to be extended to the area.
Storm Drainage
CP -5/6 does not have an improved storm drainage system and relies upon
natural drainage and drainage from road improvements to channel water to
various creeks.
Street System
CP -5/6 is accessed via Scenic Road, Taylor Road and Beall Lane from the east
and the west. Grant Road runs north and south and forms one boundary of the
two URAs. These roads are primary collectors and others roads are envisioned
in order to promote better internal circulation (see Figure 2) and to relieve
demand on existing roads that may have capacity limitations.
Irrigation District
CP -5/6 is located within the Rogue River Valley Irrigation District (RRVID).
Irrigation water is transferred via canals, laterals and some natural means. Most
of the land in these URAs is irrigated (see Figure 7).
Page 11 of 20
19
Ak
CENTRAL
POINT
Legend
Waterline Mains
Rogue Valley Sewer Services
20
Figure 5. Utilities
Urban Reserve Area CP-5A/6A
Concept Plan
Page 12 of 20