HomeMy WebLinkAboutResolution 329 - Forest Glen, Ph. VII - Tent. Plan{ ''~ ~~ L~/ ~y
PLANNING COMMISSION RESOLUTION N0. J 2~"1
A RESOLUTION GRANTING APPROVAL OF A TENTATIVE PLAN FOR
FOREST GLEN SUBDIVISION, PHASE VII
(Applicants: Gary whittle, Barry Bloomberg, James Johnson)
(37 2W Section 11A, Tax Lot 1800)
BE IT RESOLVED BY THE PLANNING COMMISSION OF THE CITY OF
CENTRAL POINT, OREGON, AS FOLLOWS:
Section 1. Nature of A lication. This is an application for
approval of a tentative plan for an 8-lot subdivision in an R--2
district of Central Point, Oregon. The Planning Commission
reviewed the application and tentative plan at a duly-noticed
public hearing on September 19, 1995.
Section 2. A roval Criteria. The criteria far approval of
this subdivision application are found in CPMC Title 16, relating
to tentative plans and subdivisions, and in Title 17, relating to
zoning and lot sizes.
Section 3. Findings and Conclusions. The Planning Commission
finds and determines as follows:
A. Tentative Plan Re uirements. The application and
tentative plan herein are in the correct form and contain all of
the information required for the same under CPMC Chapter 16.10.
B. Area and Width of Lots. The subdivision lots range in
size from 9,240 square feet to 11,765 square feet and all meet the
R-2 district lot size requirements of 6,000 square feet for
interior lots and 7,000 square feet for corner lots. The minimum
width requirements are also met, with interior lots at least 60
feet wide and corner lots at least 70 feet wide.
C. Blocks and Streets. The tentative plan proposal for the
layout and dimensions of streets and blocks is in compliance with
the requirements of CPMC Chapter 16.20 regarding streets and CPMC
Chapter 16.24 regarding blocks.
Section 4. Conditional A royal.
tentative plan approval for the within
approved, subject to the conditions lasted
imposed under authority of CPMC 16.10.090.
Passed by the Planning Commission
authentication of its passage this "L~, s
1995.
The application for
subdivision is hereby
on Exhibit "A" hereto,
and s~.gned by, me in
day of ~. `~(~~ l'_~1~~~~' r
C~~~~cc.lCr/I
Planning Commission Chairman
1 - PLANNING COMMISSION RESOLUTION NO. ~~ {092095)
ATTEST:
.~
City R r S htati ~
r~ ...
.G~~~~ day of ~ ...~> ~~ ..,... 1995.
Approved by me this ~4-. '' t
Planning Commission Chairman
2 - PLANNING COMMISS3ON RESOLUTION NO. 092095)
BXHIBIT "A"
PUBLIC WORKS DEPARTMENT
TENTATIVE PLAN CONDITIONS
FOREST GLEN Vll SUBDIVISION
GENERAL
o ORS Chapter 468,740 requires that all developments which will disturb 5 ACRES OR
MORE of land adjacent to a stream which discharges to surface waters of the State of
Oregon shall as a part of the construction permitting process submit an "Erosion
Control Plan."
The "Erosion Control Plan" shall require a ~.,I from DEQ. No construction on any
Tentative Plan storm drainage system can occur until authorization to do so has been
granted by DEQ.
o Developer shall provide and install ladder rungs approved by the Central Paint Public
Works Department for each sanitary sewer manhole with a depth greater than 3.0 feet
to the flow line of the manhole.
o Developer`s engineer shall design the water system to provide a minimum flow of 1000
g.p.m. at each fire hydrant.
o Developer shall construct all utilities, streets, and other structures discussed herein,
within rights-of-way owned, or to be owned by the City of Central Point, in accordance
with all rules, regulations, ordinances, resolutions and other applicable requirements
of the City of Central Point for the construction of this development.
o This review for the Tentative Plan submitted by the applicant was done so in
accordance with all the rules, regulations and ordinances in effect as of the date of this
review. Any modifications by Developer of this project after City Planning Commission
approval, could require resubmittal of an application, and approval by the City Planning
Commission based on the recommendation of staff responsible for this review.
o All costs associated with this Development and the conditions placed on this
Development shall be the sole responsibility of the applicantlowner.
o No construction will begin on this project or any building until such time as plans and
specifications have been reviewed and approved by the Public Works Department and
other required divisions of the City and a Construction Permit has been issued for each
portion of the project requiring a permit.
o The Final Plat of this Subdivision shall not be approved by the Planning Commission
until all conditions as herein stipulated and approved for this project have been met by
construction and acceptance thereof or bonding for construction.
o The City shall approve street stationing prior to Developer's engineer designing the
improvements for this Tentative Plan.
EXHIBIT "A"
Public Works Department
Tentative Plan Conditions
Forest Glen, Phase VII
SPECIFIC
1. All structures shall have roof drains, area drains, and crawl spaces with positive
drainage away from the structure and drain lines connected to a curb drain, or an
approved storm sewer. The developer shall provide the necessary storm drainage
improvements and iot grading to assure that all streets, lots, and all properties will
drain properly. The developer shall submit a grading plan with the construction
drawings and perform such grading and drainage improvements which satisfies this
drainage condition leaving only minor grading required for each lot during construction.
2. Construction of this development shall include street, lighting, water, sanitary sewer,
storm drainage utilities, ingress and egress improvements, and sidewalks. All
improvements shall be designed and constructed in accordance with City of central
Point Standards and Specifications for Public Works Construction.
3. The City's Engineer shall at the cast of the developer, evaluate the strength of the
native soils and determine street section design in accordance with the Public Works
Department Design Standards. The streets shall use the following design criteria:
Street Name Average Daily Traffic % Trucks
Glengrove Avenue 2,500 VT/D 5%
4. The construction drawings for this Tentative Plan shall include a Street Lighting Plan
and a Traffic Control Pian in accordance with the requirements of the City of Central
Point Public Works Department. The construction drawings shall include clear vision
areas designed to meet the City of Central Point Public Works Standards. Developer
shall pay far all costs associated with the design and installation of the street and
lighting improvements specified on these plans.
5. The construction drawings will indicate type, size and location of water mains and fire
hydrants in accordance with the City's Public Works Standards and the
recommendation of the City's Fire Chief.
6. Developer's engineer shall design the sewer system to serve the development of this
tract and all future development which will be tributary to this development.
7. Developer shall construct an adequately sized storm drainage system to provide for
runoff onto the subdivision property and from each lot. As a part of the construction
of the improvements for this Tentative Plan, Developer's engineer shall provide a
complete set of drainage calculations for sizing the storm drainage system for this
development. Developer shall submit this information to the Public Works Department
at the time construction drawings for the subdivision are submitted to the Public Works
Department far permits for construction of the storm drainage improvements. The
engineer shall use the rainfalllintensity curve obtained from the Public Works
Department for hydrology calculations.
Exhibit "A"- Forest G{en VI[
Specific Conditions-Continued
8. Service laterals shalt be property sized and configured to accommodate the dwellings
for each lot.
9. Columbine Way in this subdivision shall be changed to Glengrove Avenue.
10. An 8" ductile iron water main shall be constructed in Glengrove Avenue and looped to
the 8" line on Columbine Way.
11. Developer shall provide a minimum 15' storm drain easement between lots 214 and
215.