HomeMy WebLinkAboutResolution 841 - Approving Floodplain Dev. Permit for Twin Creeks RR X-ing improvementsRESOLUTION NO. 841
A RESOLUTION OF THE PLANNING COMMISSION APPROVING A FLOODPLAIN
DEVELOPMENT PERMIT/NO-RISE CERTIFICATE FOR CONSTRUCTION OF TWIN
CREEKS RAILROAD CROSSING ROADWAY IMPROVEMENTS WITHIN THE GRIFFIN
CREEK FLOODWAY
(File No: FP 16002)
WHEREAS, the applicant has submitted a Floodplain Development application and No -Rise
Certification to construct roadway improvements, including pavement reconstruction, and curb and gutter
and sidewalk construction in the Griffin Creek regulatory floodway on a portion of Highway 99 in Central
Point, OR 97502.
WHEREAS, the No -Rise Certification was prepared in accordance with FEMA's Guidance for "No-
Rise/No-Impact" Certification for Proposed Developments in Regulatory Floodways; and
WHEREAS, the No -Rise Certification confirms that the proposed roadway improvements will not
increase the base flood elevation or floodway profiles relative to the effective FEMA mapping; and
WHEREAS, on February 7, 2017, at a duly noticed public hearing, the City of Central Point Planning
Cornmrission considered the Applicant's request for floodplain development approval for the Twin Creeks
Railroad Crossing Floodplain Development Permit/No Rise Certification (the "Project"); and,
NOW, THEREFORE, BE IT RESOLVED that the City of Central Point Planning Commission by
Resolution No. 841 hereby approves the Twin Creeks Railroad Crossing Floodplain
Development Permit/No-Rise Certification based on the Staff Report dated February 7, 2017,
including attachments incorporated by reference (Eklnbit "A"); and
PASSED by the Planning Commission and signed by Vminaulthen'ration of its passage this 7h day of
February 7, 2017
mission Chair
A ST:
,( u� 5i-�- %,
CitARepresentative
Planning Commission Resolution No. 841 (2/7/2017)
City of Central Point, Oregon
140 S 3rd Street, Central Point, OR 97502
541.664.3321 Fax 541.664.6384
www.centralROintoregon.gov
Xcoa
CENTRAL
POINT
Oregon
STAFF REPORT
February 7, 2017
AGENDA ITEM: File No. FP -16002
Community Development
Tom Humphrey, AICP
Community Development Director
Consideration of a floodplain development application to construct Highway 99 roadway
improvements within the Special Flood Hazard Area (SFHA) and regulatory floodway for
Griffin Creek. Applicant: City of Central Point (Matt Samitore).
STAFF SOURCE:
Stephanie Holtey, CFM, Community Planner II
BACKGROUND
The City of Central Point ("Applicant") requests floodplain development approval to construct
roadway improvements within the Special Flood Hazard Area (SFHA) and regulatory floodway
for Griffin Creek (Attachment "A"). The proposed improvements are needed to complete
construction of the Twin Creeks Railroad Crossing project, which is identified in the Twin
Creeks Transit Oriented Development (TOD) Master Plan ("Master Plan") and the City's Capital
Improvement Program (CIP)(Project No. 202) as a vital link between Twin Creeks and
development east of the CORP railroad. To be approved, the Applicant must demonstrate that the
proposed improvements do not aggravate flood conditions.
Project Description:
The Twin Creeks Rail Crossing project will extend Twin Creeks Crossing easterly across the
CORP railroad tracks to create a new, signalized "T" intersection with Highway 99. Additional
project improvements include the following:
• A new at -grade railroad crossing;
• Sidewalk, curb and gutter construction along the east side of Highway 99 to the north and
south of the new intersection; and,
• Pavement reconstruction raising the grade along Highway 99 to match the grade
elevation at the intersection.
A portion of the pavement reconstruction and sidewalk improvements, including curb and gutter,
are within the Griffin Creek SFHA and regulatory floodway. In accordance with CPMC
8.24.200(A), the Applicant submitted a No -Rise Analysis and certification, which evaluates the
effective and proposed flood conditions based on construction of the Twin Creeks Railroad
Crossing project. According to the No -Rise documentation, the minor grade increases do not
increase flood elevations consistent with the City's no -rise standard.
ISSUES
There are no issues associated with this application.
FINDINGS OF FACT AND CONCLUSIONS OF LAW
The proposed floodplain development has been evaluated against the Central Point Municipal
Code (CPMC) Chapter 8.24 requirements for Flood Damage Prevention and found to comply as
evidenced by the Applicant's No -Rise documentation (Attachment `B").
CONDITIONS OF APPROVAL
No conditions of approval are recommended.
ATTACHMENTS
Attachment "A" — Floodway Development Project Location Map
Attachment `B" — No Rise Certificate and Analysis (Note: Appendices are included in the
record and available for review upon request)
Attachment "C" — Floodplain Development Application, dated December 14, 2016
Attachment "D" — Resolution No. 841
ACTION
Consider the floodplain development application and 1) approve; 2) approve with
modifications; or 3) deny the application.
RECOMMENDATION
Approve Resolution No. 841 Approving a floodplain development application to construct
Twin Creeks Railroad Crossing improvements within the regulatory floodway for Griffin
Creek.
NOTE MAP AREA SHOWN ON THISPANEL
IS LOCATED WITHIN TOWNSHIP 36 SOUTH.
RANGE 2 WEST AND TOWNSHIP 1MnTd S1LOr
37 SOUTH RANGE WEST
,'e3 --N 3n
•fl }
+23�
E
F�
i 2!0 1
I G
J
.
ATTACHMENT "A"
Twin Creeks Railroad Crossing
Project Location & Flood Map
N
n
4 &-�
[I
tai
rwn ae.w: aoumy
'11—N City of —
Central Point
410092
Profile emllne ,
Jackson County
Unincorporated
Are"
415589
r..A.m,.,,i'.
�� iarV►! �+r.�r
ZONE AE
AYW>a
` .•
IP33.3
f
•H V.
r
"--'ZONE AH
1120.01
;H
PTeSlle
ti Bas@llnN
` 12 a
n!rNI
4.
Approx limits of
,��, _HCIN/114
1 '. N
% Pavement
fi GilNCrtleE
r=� •p1
reconstruction
�%
5737
'
11 4
Extended i flowaII, ? aM1
curb and gutter -" 1267
�rs
11{f
Jackson County
pincurporatWAreas
REFLECT LOMR
•
EVISEiJ
�.�. --�
September14, 2016
� h
4�J
,�Z ►' *,
AREA w„
1 l.i
"
1' a< 415589
233 ri+4�+1 iart
Jackson County.
$ .k
r..A.m,.,,i'.
aawcer wA.
�� iarV►! �+r.�r
Ik
.00(�
f
SCALE
r
"--'ZONE AH
1120.01
;H
PTeSlle
ti Bas@llnN
` 12 a
iiilll I .rr-�ti1 rwv
4.
Approx limits of
'
% Pavement
fi GilNCrtleE
r=� •p1
reconstruction
V
Floodplain
res s �^� '
7255.0
11 4
Extended i flowaII, ? aM1
curb and gutter -" 1267
�rs
aawcer wA.
�� iarV►! �+r.�r
SCALE
r
prdis
Baseline
iiilll I .rr-�ti1 rwv
•r[ 0.4P,NlCE
�XK006�ic4YK1.A0AIIM
![�WanCpn41
—176 l r
fi GilNCrtleE
r=� •p1
Affected
'0 .
Floodplain
res s �^� '
7255.0
R
�}
.151 VIM,
REVISED TO
REFLECT LOMR
,a
EFFECTIVE;
�.�. --�
September14, 2016
� h
4�J
•ra+pl4 r rre
7YUNIN I i_RNAI IONIA.
I
ATTACHMENT "B"
Twin Creeks Rail Crossing
Floodway Impact Hydraulic Step
Analysis
September 2016 Revision 1
Prepared for:
City of Central Point
c/o ODOT Region 3
Prepared and Submitted by:
IYLIN INTERNATIONAL
-TY0NIN I ERNAI ZONAL
Purpose and Need
The City of Central point wishes to extend the Twin Creek Crossing form its current terminus west of the
CORP railroad tracks to a T intersection with the Rogue Valley Highway (HWY 063). The project requires
the grade of Hwy 063 be raised to match elevation at the intersection location, and will develop sidewalk
along the east side of the highway in both directions to connect with approaching sidewalk termini.
The project re -constructs a portion of the highway over the twin box culvert passing Griffin Creek. Per the
FEMA flood insurance map this development will be within the floodway where Griffin Creek overtops this
culvert in the 1% probability (100year) flood event.
1246.0) '+-
"IM,
Profile 'f
Baseline/ 'k `,
F Baseline
I ,iw.1lpORl11
JAM
_LQp *
i25� 1',% ANNUAL -CHANCE
`FLMD DISCHARGE
CONTAINGO
o
ew.s
rz: 1�5 zn
Approx limits of
Pavement
M1*
INSTRUCTURE ti
e
Nu7oN+AROOM wswuNrF.wacs,AM
—
JACKSON COUNTY(RIEGON
reconstruction
gnaw
1768„2327 ►/r
Affected
!i
1257.4 �f ' Floodplain
area
�
°"°^" 1�0
Extended sidewalk
1255.0
curb and gutter
_.+�=
V N ISTSTNEET
1257.r .5S3w1
REVISED TO
"
12611
REFLECT LOMR
1259.9
,6. G} c p4,
s
EFFECTIVE;
g1 } ,�'•I>.IH,s 1K
y'
U
a
September 14, 2016
nrrN
y • nn^ aa��' J
YrW17G9F
W
d1029/:1766F
1243.4
-
Ionr=.
NAY 0, 2011
Floodplain Area Affected Hwy 063 Griffin Creek Culvert
Analysis Procedures
The location under consideration is currently in public comment for map revision to capture modifications
to the intersecting Jackson Creek drainage west of the CORP Railroad alignment. At flood stage Griffin
creek overtops the bank to the north and flow is diverted northerly to the Jackson Creek basin. The
proximity of this flow modification to the project site, illustrated above, leads to the step backwater
analysis performed for that revision as the most current model capturing these already constructed
modifications within the drainage system. Therefore, the current published insurance study, Number
Twin Creeks Rail Crossing Project N a a L ) 1
Floodplain Impact Analysis (June 29, 2016)
TYUNIN rERN.ADONAL
41029V000A effective May 3, 2011, is outdated, and the pending study analysis, to be fully effective
September 2016 has been used as the basis for this no rise comparison.
The comparison analysis for this no effect documentation was acquired directly from the consultant
performing the Letter of Map Revision (LOMR), which fully re -modeled the drainage basin including Griffin
Creek. Therefore the cross sections compared do not exactly align with the 2011 effective insurance study,
and therefore no annotation of the tabular values in that study can be provided. Fortunately, the work in
question is centered about the culvert feature which provides cross sections at that location and can be
aligned with all previous flood studies providing a basis of comparison and has established confidence in
the existing conditions analysis.
The procedure uses the LOMR HEC RAS steady flow step backwater analysis model, expected to be
effective September 2016 and as developed originally by Northwest Hydraulics Consultants under contract
to the City of Central Point. No new cross section locations were developed for the proposed conditions
analysis, hence no calibration of the existing conditions is needed. All modifications have been to the deck
elevations to the existing culvert section modelled at River Sta 58+84. The culvert upstream and
downstream deck elevations were modified to reflect the proposed road profile above the culvert location
and compare to the previous existing condition.
vi
II;�M Oe�rwn ryw�!
Griffin Creek Culvert Existing Road Surface
Twin Creeks Rail Crossing Project _. P age 12
Floodplain Impact Analysis (June 29, 2016)
iYLININ ! 1 _i1NAHMIA(
a
Griffin Creek Culvert Proposed Road surface
Notably minimal changes in roadway elevation occur, the primary modification to the proposed surface is
the inclusion of drainage curb along both side of the highway. To complete the no rise the curb line
required lowering from typical design height within the limits of the culvert passing below.
The modifications to the culvert section were prepared using the Bentley InRoads design package to model
the location of the roadway gutter line. The gutter line establishes the parallel elevation and the various
features of the new roadway are installed to re -define the roadway surface for the proposed conditions
model.
Specifically the upstream culvert roadway was modified to capture drainage curb along the west edge of
the roadway to the anticipated limits of the project. The existing points in the cross section were measured
and modified to reflect the higher elevation. Downstream culvert roadway surface was similarly modified
but extended to the limits of the cross section to reflect the full length installation of new sidewalk curb
- ----- td -gutter along the east -side of the highway, In that case-th"levations-recorded are the-greatest-ofthe
back of sidewalk (gutter line + 8 inches) or the centerline of the roadway crown. The location to the limits
of the culvert required lowering of the sidewalk, similar to a driveway curb -cut, to prevent any calculated
rise at the sections examined.
Additional cross section points at the road surface were added to both upstream and downstream sections
to capture abrupt changes, for the curb along the west side of the highway (upstream) and for the concrete
barrier at the culvert along the east side of the highway (downstream).
Upon completion of these modifications HEC -RAS software was executed and the resultant predicted
water surface elevation differences compared at the local cross sections.
Results and Conclusions
Comparison of local cross sections:
Twin Creeks Rail CroainpProiect P a g e € 3
Floodplain Impact Analysis (June 29, 2016)
TYLININfFRf UV 4 )Mid,
X -Section
Station
5955.071
5884 Culvert U
5884 Culvert D
5807.13
LOMR analysis i
Water Surface 100 yr.
1256.4
1256.4
1255.6
1255.0
Proposed Surface
Water Surface 100
yr.
1256.4
1256.4
1255.6
1254.9
100 yr.
Difference
0.0
0.0
0.0
0.1
The analysis shows no rise for these four stations. Notably the rise at River Sta 58+07.13, just downstream
of the culvert is -0.1 feet reflecting a slightly increased flow velocity of the overtopping flow at the
downstream culvert end.
The final conclusion is that with the proposed sidewalk curb -cut geometry there is no calculated rise within
the vicintiy of the roadway modifications.
Disclaimer
The analysis prepared has relied on information in support of the current LOMR being considered by FEMA
to become effective September 2016. Notably at this time it is our understanding that FEMA has accepted
the modeling and the LOMR application is currently undergoing the required public review and comment
period. While every effort has been expended to verify that this model is consistent with the results as
illustrated in the currently effective insurance study, should this LOMR not be placed into effect as
scheduled and the modelling subsequently changed it may affect the input into this analysis. With that
understanding the goal of this analysis is to verify no rise to the floodway and demonstrate acceptable
localized rise for the 1_00 year flood water surface due to the planned roadway develo meet, aind
regardless of any modification to the supporting analysis it is reasonable to conclude that the specific
results for this location will remain unchanged.
Twin Creeks Rail Crossing Proieet_
Floodplain Impact Analysis
(June 29, 2016)
Page 14
Date fir :a ves1.. m Floodplain Deveiopment Permit No.�
City of Central Point Floodway Encroachment Analysis
CENTRAL No -Rise Certification
POINT
PROPERTY INFORMATION
PROPERTY OWNER'S NAME City of Central Point
PROPERTY ADDRESS (Including Apt, Unit Suite, and/or Mg. No.) OR P.O. BOX NUMBER
140 South 3rd Street
CITY STATE ZIPCOOE
Central Point Oregon 97502
PROPERTY DESCRIPTION (rAw and TaSlot Numherl BUILDING USE (e.g. Residential, Non•re0deatlei, Detached Garage, Addition, Accessory, etc,)
37 2W 03DB No tax lot Highway
FLOODWAY ENCROACHMENT ANALYSIS AND NO -RISE INFORMATION
PROJECT/ENCROACHMENT DESCRIPTION (Please be specific. Attach site plan andinclude additional pages If necessary)
Raise of grade to accommodate intersection at Twin Creeks Crossing and highway 99 results
In some adjustment to highway grade through the Griffin Creek Hoodway.
Structural encroachment es ANO T~
Fill placement qfYes 1 No
Quantity: 12& Brox, _____..:cubic yards
Material Type: Various - Goncrete AACWS and bas_ a aggregate
Material Source: Commercial supplier TSD
FIRM COMMUNITY -PANEL NO. EFFECTIVE/REVISED DATE BASE ROM ELEVATION (NAVA 14x8)
SUPPORTING TECHNICAL DOCUMENTATION
1 Report with analysis
2.
3.
COMMENTS: Analysis prepared from current LOMB model effective September 2016 to capture the most
current effects at this location.
OREGON REGISTERED PROFESSIONAL ENGINEER CERTIFICATION
I certify that I am a duly registered professional engineer licensed to practice in the 5tate of Oregon. I certify that the attached
technical data supports the fact that the proposed development described herein will not Impact the 100 -year (1% annual cha rice)
flood elevations, floodway elevations or floodway widths on the affected stream located both upstream and downstream of the
proposed development, at published or unpublished crossections in the FEMA Flood Insurance Study specified in Section a of this
No -Rise Certification.
Scott M. Nettleton P.E.
CERTIFIER'S NAME
TY Lin International
COMPANY NAME
862$!% Cascade Ave Suite 604 Beaverton OR 97008
ADORE CITY 51'ArE 2IPCO10E r
LL IsT RE DATE
Expires 12/31/2016
140 South 3rd Street I Central Point, OR 97502 1 (541) 664-7602
www.centralpointoregon.gov
Alk Floodplain Development Permit
CENTRAL Application
POINT
ATTACHMENT "C"
OFFICE USE ONLY
EC No -Rise 'CLOMR Attochments
Approved .Denied Subject to COA
Instructions: Complete all unhighliehted sections of this application form to provide a complete understanding of your development proposal.
Highlighted sections are for office use only. Please incude attachments to help clarify your proposal. These may include a site plan, elevation
drawings, detailed drawings and photographs. Refer to the application checklist for a complete list of required supporting documentation.
Incomplete applications will not be accepted. Contact the Floodplain Coordinator at 541.664.7602, Ext. 244 if you have any questions.
SITE ADDRESS: Map and Taxiot A: 37S 21117 03 -DB
Highway 99 at Twin Creeks Crossing FIRM Map& Ponel No.: a1O29C
Flood Zone: Jx Floodway BFE: 1255.0-t256.4ft. NAVD88 Base Depth: NPA jt, I Minimum OFF:
OWNER NAME: City of Central Point (Matt Samitore) APPLICANT/AGENT NAME: N/A
MAILING ADDRESS: 140 South Third Street, CP 97502 MAILING ADDRESS:
PHONE: I E-MAIL: PHONE: E-MAIL:
541.664.7602 Matt. Sam itore0centraloointoreaon.aov
As part of the Twin Creeks Rail Crossing project (construct new intersection), highway grades must be raised to match the elevation
at the new intersection and new sidewalks constructed. The highway grade adjustments and sidewalks will occur within the SFHA
and regulatory floodway. A No -Rise Analysis has been prepared and demonstrates no adverse impact.
Type of Use (Check one):
Residential
Mixed Use (residential and non-
residential)
Non-residential (commercial, accessory)
-' Elevated
11 Floodproofed (attach certification)
i_7 Manufactured Home
F Located on individual lot
Located in manufactured home park
Type of Activity (Check one):
New structure
Replacement of existing structure
Relocation of existing structure'
Addition to existing structure
Remodel to existing structure
Additions & Remodel Information:
1. Year Built:
2. Existing Bldg. Valuation: $
Source:
3. Proposed Const. Cost:
Source:
' Relocated structures are treated as new construction
' Additions and remodels that exceed 501Y of the market 4(a). Addition Type:
value of the existing structure are a substantial _'. Vertical
improvement, which requires full compliance with Ch. 8.24. J Lateral
Improvements are counted cumulatively over a 10 -year 4(b). If Lateral Addition, is it structurally
period. connected? a Yes No
1. Lowest habitable floor elevation:
3. Area of enclosed area below the BFE:
Other Structural Project Information:
feet, NAVD 88 2. Garage Slab Elevation: feet, NAVD 88
sq ft. 4. No, proposed flood openings: Total Area: so ft
Check all the proposed non-structural development activities associated with your project, as provided below.
7 Tree, vegetation and/or debris removal
i_ Bridge or culvert replacement
Excavation
qt (cu yards):
_; Stream bank stabilization
KS Fill placement
I City (cu. yards): —125
_ Watercourse alteration
Grading (attach project grading plan)
_ Subdivision with improvements in the SFHA
Fence or wall construction
Capital Imrovement Project (Functionally dependent use
V.1 Swimming pool installation
Other:
By signing below, I agree to the terms and conditions of this permit and certify to the best of my knowledge the information
contained in this application is complete, true and accurate.
Matt Samitore 12-14-2016
(PRINTED name) (SIGNED name) (pate)
ffIRIN7F.17 name)
Updated 1/13/2012
(SIGNED name)
(Date)
ATTACHMENT "D"
RESOLUTION NO. 841
A RESOLUTION OF THE PLANNING COMMISSION APPROVING A FLOODPLAIN
DEVELOPMENT PERMIT/NO-RISE CERTIFICATE FOR CONSTRUCTION OF TWIN
CREEKS RAILROAD CROSSING ROADWAY IMPROVEMENTS WITHIN THE GRIFFIN
CREEK FLOODWAY
(File No: FP 16002)
WHEREAS, the applicant has submitted a Floodplain Development application and No -Rise
Certification to construct roadway improvements, including pavement reconstruction, and curb and gutter
and sidewalk construction in the Griffin Creek regulatory floodway on a portion of Highway 99 in Central
Point, OR 97502.
WHEREAS, the No -Rise Certification was prepared in accordance with FEMA's Guidance for "No-
Rise/No-Impact" Certification for Proposed Developments in Regulatory Floodways; and
WHEREAS, the No -Rise Certification confirms that the proposed roadway improvements will not
increase the base flood elevation or floodway profiles relative to the effective FEMA mapping; and
WHEREAS, on February 7, 2017, at a duly noticed public hearing, the City of Central Point Planning
Commission considered the Applicant's request for floodplain development approval for the Twin Creeks
Railroad Crossing Floodplain Development Permit/No Rise Certification (the "Project"); and,
NOW, THEREFORE, BE IT RESOLVED that the City of Central Point Planning Commission by
Resolution No. 841 hereby approves the Twin Creeks Railroad Crossing Floodplain
Development Permit/No-Rise Certification based on the Staff Report dated February 7, 2017,
including attachments incorporated by reference (Exhibit "A"); and
PASSED by the Planning Commission and signed by me in authentication of its passage this 7`11 day of
February 7, 2017
Planning Commission Chair
ATTEST:
City Representative
Planning Commission Resolution No. 841 (2/7/2017)